Learning Innovation & Leadership Centre
June 2010
Completed Learning, Innovation & Leadership Centre
May 2010
External cladding almost completed.
April 2010
View showing the internal framework prior to cladding being fitted. This view shows the roofing sheets in place.
April 2010
Frame and roof supports prior to roofing and cladding being applied.
April 2010
Internal walls prior to cladding being installed.
March 2010
Initial framework and roof structure in place.
February 2010
Area prepared ready for pouring of slab which is being simultaniously poured with the Green Skills Centre floor.
February 2010
Trench filled with pipes extending for stormwater.
February 2010
Stormwater pipes being prepared in trenches under slab area.
January 2010
Pump house and pipe work that manages all the water services for the shared site for the two projects, including the Green Skills Trade Centre.
January 2010
Trenches housing the extensive underground water supply services, underground fire hydrant services filled and ready for slab. This is a shared site for two projects, the other being the Green Skills Trade Centre.
October2009
View of clearing and levelling completed in preparation for footings, slab construction, underfloor heating and plumbing pipework.
October 2009
Site plan indicating position that panoramic shot was taken from of the Learning Innovation and Leadership Centre.
September 2009
The site where a new Institute Office in Orange to allow the relocation of staff from current leased premises.